Vernon County, WI
STH 131 Realignment

Final plan preparation of six concrete haunched slab structures and two PI girder structures; several curved, all with aesthetic treatments, including special railings and form lined finish. Structures vary in length from 92 to 365 feet (most 200′ to 300′). First phase (4 of 8 bridges) completed in 2 months. Also, final plan preparation of 4 retaining wall structures (1100 feet total length). Wall types include post and panel, sheet piling with concrete form liner fascia, and split block retaining walls. Project was selected this winter for WisDOT Construction Award.